The article sets out how often permissions carried one, what the conditions covered, and how long councils took to decide the applications that discharge them.

We drew a random sample of 8,174 full planning permissions that London councils granted in 2022, 2023 and 2024, and read the conditions on 7,897 of them. We also counted the 47,462 discharge applications that the 33 London planning authorities decided between January 2024 and October 2026.

How many permissions carried a pre-commencement condition

A pre-commencement condition appeared on 21% of the permissions (1,675 of 7,897). The share rose with the size of the scheme, as the table shows.

Scheme Permissions with a pre-commencement condition Median number of such conditions
Alterations, extensions and changes of use with no new homes 11% (773 of 6,559) 1
1 to 9 new homes 63% (732 of 1,153) 2
Major schemes (10 or more homes, or 1,000 square metres or more of floorspace) 91% (170 of 185) 4

The share with a pre-commencement condition was 47% in Hillingdon (68 of 142) and 7% in Islington (27 of 343). These figures are not adjusted for the kinds of scheme each council receives.

What the conditions covered

The table shows the subjects of the conditions on the 1,675 permissions that had one.

Subject of the pre-commencement condition Share of the 1,675 permissions
Construction management, logistics or method statement 53% (892)
Materials or detailed design 18% (308)
Trees or tree protection 16% (278)
Noise, vibration or sound insulation 15% (267)
Landscaping or boundary treatment 14% (243)
Drainage or flood risk 13% (232)

How long councils took to decide discharge applications

The law gives a council eight weeks to decide a discharge application, unless the applicant agrees a longer period. London councils decided 56% of applications within eight weeks (26,734 of 47,462), and the median was 56 days. They took more than 13 weeks to decide 25% (12,033 of 47,462). The registers do not show where a longer period was agreed.

The chart shows the share decided within eight weeks in 26 councils. It was 86% in Sutton (518 of 600) and 29% in the City of London (539 of 1,848).

Share of discharge applications decided within eight weeks, by London council
Anyone may reuse this chart with credit to PlanningLedger and a link to this page.

How applications for pre-commencement conditions were decided

We linked 1,287 decided discharge applications to pre-commencement conditions in the sample. Councils refused 9% of them (122 of 1,287). They refused 12% of those that dealt with a construction management condition (61 of 474) and 17% of those that dealt with drainage (22 of 124).

Councils refused applications that dealt with several conditions more often, as the table shows. It covers the discharge applications made on the sampled permissions, whatever the condition.

Conditions dealt with in one application Decided within eight weeks Refused
One 63% (1,531 of 2,411) 9% (221 of 2,411)
Two or three 59% (406 of 683) 13% (89 of 683)
Four to six 54% (117 of 214) 17% (38 of 214)
Seven or more 42% (33 of 77) 20% (16 of 77)

On 747 permissions, the earliest application for a pre-commencement condition was validated a median of 152 days after the permission. On 478 permissions where each pre-commencement condition had an approved application, the last approval came a median of 264 days after the permission.

Details that were refused and details that were approved

The table gives examples, each linked to the council's copy of the decision.

Subject Details that were refused Details that were approved
Construction management plan The highway engineer asked for "details of the size and frequency of the vehicles expected on site as well swept path analysis". (Kingston upon Thames, refused August 2024) A second application for the same site added a swept path analysis and was approved in 38 days. (Kingston upon Thames, approved September 2024)
Ten conditions in one application The council found five acceptable and refused the application, stating that "as a result of five conditions not being discharged the application fails in its entirety". (Enfield, refused December 2024) Five conditions in one application were approved 56 days after validation. (Kingston upon Thames, approved June 2022)

A checklist for builders

  1. List the conditions that need approval before work starts when the decision notice arrives. A pre-commencement condition appeared on 63% of permissions for 1 to 9 new homes.
  2. Prepare the construction management plan before the other details. It was the subject on 53% of the permissions with a pre-commencement condition.
  3. Give vehicle sizes, routes and a swept path analysis in that plan. Kingston upon Thames refused a plan without them and approved one with a swept path analysis seven weeks later.
  4. Weigh a separate application for each condition where one refusal would delay the others. Councils refused 9% of applications that dealt with one condition and 20% of those with seven or more.

Figures were counted on 25 November 2026 from council decision notices and planning registers. The conditions figures come from a random sample of full permissions granted in 2022 to 2024 by London councils other than Brent. Links between applications and conditions are those we could trace. The chart leaves out seven councils whose dates could not be checked. This article is research, not advice.